New Kwekwe-Lupane highway to cut travel distance from Harare to Victoria Falls by 200km

Date:

WORK on the new Kwekwe-Nkayi-Lupane highway that will subtract 228km from the current 876km distance between Harare and Victoria Falls, is fast gathering pace.

The five-year project that started earlier this year is a Public- Private-Partnership (PPP) between a local firm, Road Trackers Construction and government that will see construction of 170km of tar across Midlands and Matabeleland North provinces.

According to Brighton Vundla, the Road Trackers Construction project manager, the road which is being constructed under government’s Emergency Road Rehabilitation Programme (ERRP), is set for completion in 2029.

Motorists travelling between Harare and Victoria Falls, with no business south of Kwekwe, will turn right in the gold rich town towards Tiger Reef, go via Silobela, Nkayi and connect with the Bulawayo-Victoria falls highway at Lupane.

As a result, they will cut on an almost three-hour drive between Kwekwe and Bulawayo and three more hours from Bulawayo to Lupane.

The number of toll plazas one passes through will also be considerably cut.

“This project will shorten travel distance between Harare and Victoria Falls,” said Vundla,

“We are expecting to do 30km on the Matabeleland North side and another 30km in Midlands province next year. We will have a team which will be working from Kwekwe.”

The new road will have two toll plazas and two weigh bridges as per Zimbabwe National Road Authority (ZINARA) specifications. Weigh bridges will also be built on the Bulawayo – Victoria Falls highway which is currently undergoing massive rehabilitation.

Added Vundla: “We will be putting two toll gates and two weigh bridges because we want to safeguard this infrastructure from heavily loaded trucks coming from Hwange.”

Hwange is the main source of Zimbabwe’s coal, a mineral crucial not just in the production of electricity but steel in the Midlands.

With Zimbabwe’s rail on a virtual standstill, companies have been using trucks to transport coal across the country, a situation that is playing a huge role in destruction of roads.

“We are not simply waiting on government to fund rehabilitation and construction of roads; we are being innovative. This is a Public-Private-Partnership,” said Joy Makumbe the permanent secretary in the Transport Ministry.

“They put in their money for the construction of this road, including toll plazas and weigh bridges that will be on this road. Our mathematicians then calculated how long it will take for them to recoup their investment before government takes over full ownership of the road.”

The Lupane stretch towards Nkayi has seen tracts of land being cleared for the new road, which in the past was just a donkey cart pathway popularly known as Fighting Road.

Work on 35km is already at an advanced stage, with 15km at sub-grade level, another 20km on base three.

Your Opinion Poll

Is Kudakwashe Tagwirei emerging as a serious contender to succeed President Emmerson Mnangagwa?

Related articles

Zimbabwe seal epic Test series victory after dramatic late show

Zimbabwe secured an epic victory in the two-match Test series against Afghanistan after a dramatic 57-run win in...

Harare man in court for using stranger’s identity to obtain birth certificate, ID, passport

A Harare man is in trouble after allegedly using another person's driver's licence to secure a birth certificate,...

Come and claim compensation – Harare mayor tells residents whose houses were illegally demolished 

After Harare City Council went on a rampage recently, demolishing houses, Mayor Jacob Mafume says those aggrieved should...

‘I am still young enough to serve till 2030’— frail VP Mohadi says as exit likely to jolt another ex-military commander into presidium  

VICE President Kembo Mohadi, who has appeared increasingly frail in recent years, says he remains fit enough to...